B414 Complex at Springfields, Preston

 

The project entailed the removal of a 50m high process tower and the subsequent remediation of the ground upon which the tower stood. The building was situated within close proximity to a live process area. This meant that an important consideration in the planning process was the minimisation of any disruption that the work may cause. The ground remediation included the removal of substantial foundations and constant monitoring for radiological contamination.

 

Client : BNFL

Value : £560k