B215 High Level Waste Storage Plant at Sellafield

 

A range of tasks including: 

Evaporator B project, involving a series of plant improvements to an existing evaporator to help improve performance and evaporative capacity.

 

Steam Improvements, involving the upgrade of the condensate and high pressure steam systems within HALES. Over 1km of stainless steel pipework, ranging from 8nb to 200nb was installed.

 

Intermediate Heat Exchanger project, involving the integration of an IHX within existing pipework configurations of the cooling tanks.

 

Client : Sellafield Ltd

Value : £5.5m